Valero says repairs complete at Delaware City

Related Topics

NEW YORK, April 3 | Thu Apr 3, 2008 4:09pm EDT

NEW YORK, April 3 (Reuters) - Valero Energy Corp (VLO.N) has completed repairs on its gasoline-making fluid catalytic cracking unit at its 210,000-barrel-per-day Delaware City, Delaware, refinery.

Repairs at Valero's 275,000 bpd Aruba refinery, which were scheduled to be completed in early April, are still ongoing, a company spokesman said on Thursday.

"With the Delaware City FCC, the repairs are complete but we are not discussing rates at specific units due to our statement that rates at some of our FCCs were cut back due to market conditions and high gasoline inventory levels," spokesman Bill Day said. (Reporting by Rebekah Kebede and Haitham Haddadin)

Related Quotes and News

Company
Price
Related News
Comments (0)
This discussion is now closed. We welcome comments on our articles for a limited period after their publication.