FBI's new computer system facing more costs, delay

WASHINGTON Wed Mar 31, 2010 5:16pm EDT

Related Topics

WASHINGTON (Reuters) - A long-running effort to upgrade FBI computerized case files faced additional big cost overruns and a new delay, the U.S. Justice Department's inspector general said in a report issued on Wednesday.

The Federal Bureau of Investigation and the contractor Lockheed Martin Corp were renegotiating the budget -- last estimated at $451 million -- as well as the schedule and some of the work to be performed, the report said.

The system, known as Sentinel, had been expected to be completed by September but FBI Director Robert Mueller told Congress earlier this month it would be delayed until 2011.

"We have significant concerns with the rate and cost at which Sentinel's development is progressing," the report said. "The FBI will require significant additional time and funding to address these issues."

The report did not detail how much more it would cost, but the FBI said it planned to ask Congress for permission to take money from other technology programs to cover the latest overruns, according to the report.

There have been problems with FBI computer systems for more than a decade. The September 11 attacks in 2001 prompted Mueller to try to speed up a massive upgrade.

Dissatisfied with the programs Lockheed has delivered so far, the FBI issued a partial stop-work order on March 3 so that problems could be addressed.

In tests of parts of the new system under development, 82 percent of users reported it made their tasks much harder to complete than under existing practices.

One user said it took more than four minutes to attach a picture to a file and the process could not be stopped once started. Additionally, 91 percent of testers reported that messages to other FBI employees failed to go through.

The company said it was working with the FBI to resolve the issues but noted that thousands of FBI agents and staff were already using the Sentinel system.

"We are focusing on adjustments to the system to better align it with user priorities and expectations," Lockheed said. The company also plans to have a revised plan soon.

The FBI said in a statement it too expected to provide a new schedule and cost estimate soon and the problems did not affect its ability to do its job.

"The system works; we want it to work better," the agency said.

(Reporting by Jeremy Pelofsky, editing by Alan Elsner)

FILED UNDER:
We welcome comments that advance the story through relevant opinion, anecdotes, links and data. If you see a comment that you believe is irrelevant or inappropriate, you can flag it to our editors by using the report abuse links. Views expressed in the comments do not represent those of Reuters. For more information on our comment policy, see http://blogs.reuters.com/fulldisclosure/2010/09/27/toward-a-more-thoughtful-conversation-on-stories/
Comments (2)
Captaingh wrote:
Slow, cost overruns, hard to use, and etc.
You think this is bad, just wait until the Feds and some huge software contractor gets a hold of healthcare!

Mar 31, 2010 5:57pm EDT  --  Report as abuse
Mafettig wrote:
Even the Department of Redundancy Department is upset that this is happening “We have significant concerns with the rate and cost at which Sentinel’s development is progressing,” the report said. “The FBI will require significant additional time and funding to address these issues.” Who is upset about the rate and cost? Who needs more money and more time? Who is holding up the show again?

Mar 31, 2010 8:44pm EDT  --  Report as abuse
This discussion is now closed. We welcome comments on our articles for a limited period after their publication.

A tourist takes a plunge as she swims at Ngapali Beach, a popular tourist site, in the Thandwe township of the Rakhine state, October 6, 2013. Picture taken October 6, 2013. REUTERS/Soe Zeya Tun (MYANMAR - Tags: SOCIETY) - RTR3FOI0

Where do you want to go?

We look at when to take trips, budget considerations and the popularity of multigenerational family travel.   Video