WRAPUP 5-Enbridge fixing key US pipeline in bid to restart

Tue Sep 14, 2010 6:56pm EDT

Related Topics

 * Enbridge Line 6A to be repaired Tues, restart uncertain
 * Enbridge: regulators may not require formal restart plan
 * US gov't says pipeline can't restart until deemed safe
 * Small Line 10 in New York resumes flows after 1-day halt
 * Oil prices fall as traders expect quick restart
 (Recasts, adding details and analyst comments)
 By Joshua Schneyer
 NEW YORK, Sept 14 (Reuters) - Canada's Enbridge (ENB.TO)
said Tuesday it was near to completing repairs on its
U.S.-bound 6A oil pipeline, and might be able to restart the
line without submitting to a lengthy formal approval process
from U.S. regulators.
 Enbridge and U.S. pipeline regulators said they were
working together to determine when the 670,000 barrel-per-day
(bpd) oil pipeline could restart, after a hole in the line
leaked 6,100 barrels in Illinois last Thursday. No restart date
has been set yet.
 Expectations that the line could resume shipments soon
helped to knock oil prices down from one-month highs on
Tuesday. Line 6A ships about 5 percent of U.S oil imports.
 "We don't know yet what is required by regulators, but we
may not be required to issue a formal restart plan," company
spokeswoman Terri Larson told Reuters.
 <^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
 TAKE A LOOK-Enbridge crude line shut      [ID:nN10265810]
 Factbox on refineries                     [ID:nN13195749]
 Factbox on outage impact                  [ID:nN13190665]
 Factbox on pipelines feeding the Midwest  [ID:nN10275799]
 History of Enbridge's pipeline spills     [ID:nN10254087]
 Graphic on Enbridge pipeline configuration:
 link.reuters.com/qyz52p
 ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^>
 Restarting 6A will involve regulatory oversight, DOT said
on Tuesday, without specifying what measures must be taken.
"Enbridge will not restart this line until (regulators are)
satisfied that the company's repair and follow up plans ensure
the safety of the community and the environment," a spokeswoman
for the DOT's Pipeline and Hazardous Materials Safety
Administration said.
 Depending on what regulators require of Enbridge, the
pipeline could restart almost immediately or face a prolonged
delay that could crimp crude supplies to the industrial Midwest
and continue to push up U.S. oil prices.
 The U.S. Department of Transportation still has not
approved Enbridge's formal plan to restart a smaller line
called 6B, which has been shut for more than seven weeks after
a major leak in Michigan.
 Enbridge said it was welding a stretch of new pipe to
replace a leaky area of Line 6A it removed from the ground on
Monday. The line could be fixed by late Tuesday if X-rays
showed the seams were secure, Larson said.
 "My guess is they may get this (6A) pipeline back up and
running without having to jump over too many hurdles, since it
hasn't been out for long" said Joseph Arsenio of Arsenio
Capital Management in Larkspur, California.
 "These pipeline outages have helped push oil prices up and
any news of a restart will put pressure on prices."
 Oil prices rose in recent days on concern Enbridge may face
lengthy regulatory delays before restarting Line 6A, a key,
467-mile (752-km) line from northern Wisconsin to Indiana.
 Enbridge has yet to receive permission from regulators to
restart its 6B pipeline that leaked oil in Michigan during
July, although it has been repaired since August.
 The Enbridge pipeline leaks have come at a time when energy
industry safety regulations are under a spotlight following the
recent, massive BP Plc (BP.L) (BP.N) oil spill in the Gulf of
Mexico.
 U.S. oil futures CLc1 had touched a month-long high
earlier Tuesday on concerns for long restart delays. They later
dropped 39 cents to settle at $76.80 a barrel, in part on
expectations that the line could restart in short order.
The 190,000 barrel-per-day 6B has been shut since a Michigan
leaked of about 19,500 barrels in July.  
Larson said that the requirements to restart 6A might be
different from 6B because DOT pipeline regulators had issued
Enbridge a so-called Corrective Action Order on 6B this year,
ordering the company to take several formal steps to address
safety concerns on that line.
Enbridge hasn't received any such orders on its 6A line,
which may affect the restart process.
"We may not need to go through the same steps to restart
6A," Larson said.
A Congressional transportation committee plans to hold a
hearing on Wednesday with Enbridge executives including chief
executive Patrick Daniel in Washington. Regulators may grill
the company about its recent oil spills and discuss pipeline
safety at the hearing. 
 A FIX FOR LINE 6A
 Repairs on Line 6A in Romeoville, Illinois, are the first
step in restoring flows on a conduit that, before the spill,
was shipping 459,000 barrels a day of Canadian crude to a
half-dozen Midwest U.S. refineries, as well as toward Cushing,
Oklahoma, the delivery point for U.S. oil futures.
 Meanwhile, Enbridge said Tuesday it had resumed operations
on a separate, smaller pipeline in New York state that was shut
down late on Monday on suspicions a tiny volume of crude had
leaked, the company said.
 Enbridge found no indication of a leak on the 91-mile
(146-km) 70,000 bpd Line 10, which runs from Southern Ontario
into New York. The company plans to continue closely monitoring
the line for 24 hours.
 The shutdown of 6A and 6B combined with Line 10 on Monday
meant three stretches of Enbridge pipeline with a combined
capacity of 930,000 bpd were shut.
 The 6A line was the largest. Canada has exported nearly 2
million barrels per day (bpd) of crude oil to the United States
this year, making it by far the country's largest foreign
supplier. [ID:nN30180559]
 Enbridge's Toronto-traded shares rose 21 cents to C$52.09
on Tuesday.
 The Calgary-based pipeline operator was allowed to restart
its biggest crude export line within a week of a major 2007
explosion that killed two workers in Minnesota, although the
company was later fined $2.4 million for the incident.
 (Reporting by Joshua Schneyer and Selam Gebrekidan in New
York, Tim Gardner in Washington and Erwin Seba in Dallas;
Editing by Marguerita Choy and Lisa Shumaker)







FILED UNDER:
Comments (0)
This discussion is now closed. We welcome comments on our articles for a limited period after their publication.