Entergy to shut Vermont Yankee for $100 mln refuel
* Refuel will cost Entergy about $100 million
* Entergy wants to run plant for another 20 years
* Vermont wants reactor shut in 2012
Oct 6 (Reuters) - Entergy (ETR.N) will shut its Vermont
Yankee nuclear power plant this weekend to begin a $100 million
refueling outage, a spokesman for the U.S. energy company said
on Thursday, as it awaits a judge's decision on whether it can
keep running the plant beyond next year.
Entergy will shut the 620-megawatt plant in Vermont on Saturday, Oct. 8, for a planned refueling and maintenance outage, the spokesman said.
The unit was operating at 80 percent of capacity early Thursday, according to a report by the U.S. Nuclear Regulatory Commission.
Entergy wants to keep running the plant for another 20 years, while Vermont wants it shut in 2012.
Entergy decided to go forward with the refueling outage in July despite the upcoming court case. A refueling usually lasts about a month.
That was long before the September trial when the Honorable J. Garvan Murtha of the U.S. District Court for the District of Vermont in Brattleboro heard Entergy's lawsuit seeking to block the state from shutting the plant next year when the reactor's original federal operating license was to expire.
Entergy said it had to make a decision on the refueling over the summer because it takes time to buy and manufacture the fuel. Entergy has said the refueling outage would cost about $100 million - $65 million for the fuel and $35 million for the refueling work.
Entergy said in court papers it would cost millions to return the fuel assemblies to the vender to be redesigned for use in another reactor. Energy experts have said Entergy would not be able to return the fuel once it starts burning it when the plant exits the refueling outage.
No matter what the judge decides, this case is likely to be tied up in court appeals for years, the parties have said.
The NRC granted Entergy a new license to run for another 20 years in March 2011.
The state wants the plant shut under an agreement Entergy entered into in 2002 when the New Orleans-based company bought the plant. Under that agreement, Entergy agreed to seek permission from the Vermont Public Service Board before running the plant beyond March 2012 when the original 40 year operating license was to expire.
But the state Senate in early 2010 blocked the Public Service Board from considering Entergy's request to continue running the plant and after much - often heated - discussion between Entergy and Vermont, Entergy sued in federal district court to block the state from shutting the plant. ----------------------------------------------------------- PLANT BACKGROUND/TIMELINE STATE: Vermont COUNTY: Windham TOWN: Vernon OPERATOR: Entergy Nuclear OWNER(S): Entergy Corp CAPACITY: 620 MW UNIT(S): General Electric Boiling Water Reactor FUEL: Nuclear DISPATCH: Baseload COST: $183 million TIMELINE: 1972 - Reactor enters commercial service 2002 - Entergy buys reactor for $180 million from
Vermont Yankee Nuclear Power and enters a
10-year power purchase agreement to sell power
back to the former owners for about 4.5 cents
per kilowatt hour Jan 2006 - Entergy files with NRC to renew the original
40-year operating license for an additional 20
years Jan 2010 - Entergy identifies tritium leak Feb 2010 - Vermont Senate votes 26-4 against authorizing
the Vermont Public Service Board to issue a
certificate of public good that would allow for
the license renewal. Vermont is the only state
in the nation with the authority to block a
license renewal. The state gained that
authority when Entergy bought the plant Mar 2010 - Entergy stops tritium leak Nov 2010 - Entergy mulls sale of Vermont Yankee Mar 2011 - NRC approves of 20 year extension of operating
license Mar 2011 - Entergy drops plan to sell plant Apr 2011 - Entergy files complaint in federal district
court in Vermont to block the state from
forcing the plant to cease operation in March
2012 when the original operating license was to
expire Jul 2011 - Entergy decides to spend about $100 million to
refuel the reactor in October ($65 million for
the fuel and $35 million for the refueling
work) Sep 2011 - Trial in federal district court before the
Honorable J. Garvan Murtha Oct 2011 - Entergy to shut reactor for refueling Oct-Dec 2011 - Judge Murtha expected to decide on lawsuit Mar 21, 2012 - Reactor to shut unless state approves of
extension or Entergy wins court case to keep
reactor operating or court appeals keep plant
alive Mar 2032 - Renewed license expires (Reporting by Scott DiSavino in New York)