UPDATE 1-Delayed Subsea 7 gear on its way to Brazil project -BG

Fri Jul 26, 2013 9:22am EDT

Related Topics

LONDON, July 26 (Reuters) - The first of four giant riser systems that engineering group Subsea 7 is building for Brazilian offshore oil fields was ready to sail on Friday, energy firm BG said, following long, costly delays.

Subsea 7 warned last month it was suffering a series of issues at its $1 billion ultradeep GuarĂ¡-Lula project, resulting in a cost blowout and a six-month delay in the offshore phase of the contract for the riser systems - subsea piping to carry oil.

"The first of the four buoyancy-supported risers was due to sail this morning," said Chris Finlayson, chief executive of BG, one of the partners in the Guara and Lula fields operated by Petrobras.

"It will then take around three weeks to tether that in place, at which point the steel catenary risers can start to be installed," Finlayson said.

Finlayson said the Subsea 7 delay was not affecting BG's timetable in development of the fields.

Subsea 7 declined to comment.

It had predicted last month that the first of four riser systems would sail in mid-July, conditions permitting. The engineering company is assembling the systems in Brazil, where they are then loaded for transport offshore.

Subsea 7 shares were down about 0.4 percent in Oslo.