VIENNA Dec 9 (Reuters) - Austrian energy company EVN is seeking damages of about 600 million euros ($821 million) from Hitachi over delays to a power plant, it said on Monday.

EVN, which is a 49 percent shareholder in a special purpose entity created for the construction of the Walsum 10 plant, said it was instituting arbitration proceedings against Hitachi and a court action against an insurer.