INTERVIEW-TransCanada readies for Gulf Coast pipeline start

Tue Dec 17, 2013 1:09pm EST

Related Topics

(Adds additional comment and detail from executive interview)

By Scott Haggett and Nia Williams

CALGARY, Alberta Dec 17 (Reuters) - TransCanada Corp expects its new 700,000-barrel-per-day Gulf Coast oil pipeline to begin service on Jan. 22, Chief Executive Russ Girling said in an interview on Tuesday.

The company is currently filling the Cushing, Oklahoma, to Port Arthur, Texas, pipeline with the 3 million barrels of crude oil needed before it can be placed into normal operation.

Initial testing is showing no issues with the line and shippers were told of the planned in-service date on Monday.

"We need to make sure that we continue to test things as we load the pipeline with oil," Girling said. "Based on our current estimates, January 22 is what we've told our shippers for start-up."

The Gulf Coast line is the southern leg of TransCanada's controversial Keystone XL project, which, more than five years after the initial filing, is still awaiting a final decision from the Obama Administration.

The start-up of the Gulf Coast project will give Canada's oil sands producers their first large-scale access to the refining hub on Texas' Gulf Coast. It could also help alleviate steep discounts on Canadian crude, which dropped to more than $40 per barrel below the West Texas Intermediate benchmark last month.

Girling said much of the oil on the line will come from shippers on the company's existing 590,000 bpd Keystone pipeline, which takes crude from Hardisty in central Alberta to Cushing.

"We are now actually connected all the way to the Gulf Coast," Girling said. "The shippers (on the Keystone line) have the ability to not deliver at Cushing, they can deliver right through to the Gulf Coast. So we actually have ... a contiguous system that has the ability, once Gulf Coast is up and running, to deliver 600,000 barrels per day to the coast."

Girling said oil that would have gone to Cushing and Wood River, Illinois, Keystone's two existing delivery points, can be diverted to Texas refineries if prices warrant.

"Right now the gulf coast is priced higher than mid-continent barrels," he said. "So right now all of our shippers on the base system will want to take their barrels in that direction."

The Gulf Coast line will also take oil from shippers at Cushing who signed up for space on the line prior to construction. Girling said those customers will retain the right to ship on the project after the northern leg of the Keystone XL project is complete.

The Gulf Coast line will also take some Cushing crude from shippers who have not signed binding contracts for capacity on the line, however that group will lose their access to the line when the northern leg of the project is complete, Girling said.

TransCanada shares were up 5 Canadian cents to C$46.78 in afternoon trading on the Toronto Stock Exchange. (Editing by Gerald E. McCormick and Phil Berlowitz)

FILED UNDER:
A couple walks along the rough surf during sunset at Oahu's North Shore, December 26, 2013. REUTERS/Kevin Lamarque

Find your dream retirement town

Florida? Hawaii? Reuters has teamed up with Zillow to give you the power to customize a list of your best places to retire.  Video | Full Article