• Most Popular
  • Most Shared

FACTBOX: Venues for the 2008 Beijing Games

Tue Apr 29, 2008 7:44pm EDT

(Reuters) - The following are key facts on the 16 new, 8 temporary and 13 existing venues for the 2008 Beijing Olympic Games:

Sports

NEW VENUES

National Stadium: (ceremonies, athletics, soccer)

Construction began: December 24, 2003

Completed: first test event on April 18, 2008

Capacity: 80,000 permanent, 11,000 temporary

Nicknamed the "Bird's Nest"

National Indoor Stadium (artistic gymnastics, trampolining, handball)

Construction began: May 28, 2005

Completed: November 22, 2007

Capacity: 18,000 permanent, 2,000 temporary

National Aquatics Centre (swimming, diving, synchronized swimming)

Construction began: December 24, 2003

Completed: delivered on January 28 2008

Capacity: 6,000 permanent, 11,000 temporary

Nicknamed the "Water Cube"

Beijing Shooting Range

Construction began: July 13, 2004

Completed: July 28, 2007

Capacity: 2,170 permanent, 6,430 temporary

Laoshan Velodrome (track cycling)

Construction began: October 30, 2004

Completed: December 2007

Capacity: 3,000 permanent, 3,000 temporary

Beijing Olympic Basketball Stadium

Construction began: March 29, 2005

Completed: January 14, 2008

Capacity: 14,000 permanent, 4,000 temporary

Shunyi Rowing/Canoeing Park

Construction began: May 2005

Completed: delivered on July 28, 2007

Capacity: 1,200 permanent, 25,800 temporary

Beijing University of Technology Gymnasium (badminton, rhythmic gymnastics)

Construction began: June 30, 2005

Completed: September 30, 2007

Capacity: 5,767 permanent, 1,741 temporary

China Agriculture University Gymnasium (wrestling)

Construction began: September 15, 2005

Completed: delivered on August 18 2007

Capacity: 6,000 permanent, 2,500 temporary

University of Science and Technology Beijing Gymnasium (judo, taekwondo)

Construction began: November 18, 2005

Completed: November 2007

Capacity: 4,080 permanent, 3,932 temporary

Peking University Gymnasium (table tennis)

Construction began: September 17, 2005

Completed: December 2007

Capacity: 6,000 permanent, 2,000 temporary

Olympic Green Tennis Centre

Construction began: March 23, 2006

Completed: delivered on October 1, 2007

Capacity: 17,400

Qingdao Olympic Sailing Centre

Construction began: May 2004

Completed: March 2008

Capacity: 9,000

Qinghuangdao Olympic Sports Centre Stadium (soccer)

Construction began: May 2002

Completed: July 2004

Capacity: 33,000

Tianjin Olympic Centre Stadium (soccer)

Construction began: August 2003

Completed: August 16, 2007

Capacity: 80,000

Shenyang Olympic Sports Centre Stadium (soccer)

Construction began: March 1, 2006

Completed: July 2007

Capacity: 60,000

TEMPORARY

Olympic Green Hockey Field (hockey)

Construction began: December 28, 2005

Completed: August 2007

Capacity: 17,000

Olympic Green Archery Field (archery)

Construction began: December 28, 2005

Completed: August 2007

Capacity: 5,384

Fencing Hall (fencing, modern pentathlon)

Construction began: April 28, 2005

Completed: September 2007

Capacity: 5,900

Wukesong Baseball Field

Construction began: December 22, 2005

Completed: August 2007

Capacity: 15,000

Chaoyang Park Beach Volleyball Ground

Construction began: December 28, 2005

Completed: August 2007

Capacity: 12,200

Laoshan Bicycle Moto Cross (BMX) Venue

Construction began: December 30, 2006

Completed: August 2007

Capacity: 4,000

Triathlon Venue

Construction began: April 2007

Completed: September 2007

Capacity: 10,000

Urban Road Cycling Course

Construction began: April 2007

Completed: April 2008

Capacity: 3,000

EXISTING

Olympic Sports Centre Stadium (modern pentathlon)

Renovation began: April 1, 2006

Completed: September 2007

Capacity: 38,000 permanent, 2,000 temporary

Olympic Sports Centre Gymnasium (handball)

Renovation began: April 1, 2006

Completed: September 2007

Capacity: 5,000 permanent, 2,000 temporary

Workers' Stadium (soccer)

Renovation began: April 18, 2006

Completed: February 2008

Capacity: 62,000

Workers' Indoor Gymnasium (boxing)

Renovation began: December 23, 2005

Completed: November 2007

Capacity: 12,000 permanent, 1,000 temporary

Capital Indoor Stadium (volleyball)

Renovation began: May 18, 2006

Completed: November 2007

Capacity: 17,500

Ying Tung Natatorium (water polo, modern pentathlon)

Renovation began: April 1, 2006

Completed: September 2007

Capacity: 4,852

Laoshan Mountain Bike Course

Renovation began: May 31, 2006

Completed: September 2007

Capacity: 2,000 temporary seats, 15,000 standing

Beijing Institute of Technology Gymnasium (volleyball)

Renovation began: February 8, 2007

Completed: September 2007

Capacity: 5,000

Beijing University of Aeronautics and Astronautics Gymnasium (weightlifting)

Renovation began: January 31, 2007

Completed: December 2007

Capacity: 3,400 permanent, 2,600 temporary

Beijing Shooting Range Clay Target Field

Renovation began: March 24, 2006

Completed: August 2007

Capacity: 3,394 permanent, 1,605 temporary

Fengtai Softball Field (softball)

Renovation began: July 28, 2005

Completed: July 2006

Capacity: 5,000 permanent and 5,000 temporary seats

Hong Kong Equestrian Venue (equestrian)

Renovation began: start of 2007

Completed: May 2007

Capacity: 20,000

Shanghai Stadium (soccer)

Renovation began: 2006

Completed: 2007

Capacity: 56,000

(Compiled by Ian Ransom and Liu Zhen)

("Countdown to Beijing Olympics" blog at blogs.reuters.com/china)



More from Reuters

Photo

Democrats gain 60th vote on health bill

WASHINGTON (Reuters) - Senate Democrats reached a compromise on Saturday with the last holdout senator that secured the 60 votes they need to pass a broad healthcare overhaul sought by President Barack Obama.

A woman shops at a Sam's Club store, a division of Wal-Mart Stores, in Bentonville, Arkansas June 4, 2009. REUTERS/Jessica Rinaldi

The food-stamp economy

On the last day of every month, shoppers at Walmart load their carts with food and household items and wait for the midnight hour. Is this the new normal in America?  Full Article 

Two men shake hands in a file photo.    REUTERS/File

Let's make a deal

The battered M&A sector will make a tepid recovery in the coming year and three hot sectors will lead the way, according to a Thomson Reuters analysis.  Full Article