FACTBOX: Venues for the 2008 Beijing Games

Sun Jul 6, 2008 9:11pm EDT

(Reuters) - The following are key facts on the 16 new, 8 temporary and 13 existing venues for the 2008 Beijing Olympic Games:

World  |  Television  |  China

NEW VENUES:

- National Stadium: (ceremonies, athletics, soccer)

Construction began: December 24, 2003

Completed: first test event on April 18, 2008

Capacity: 80,000 permanent, 11,000 temporary

Nicknamed the "Bird's Nest"

- National Indoor Stadium (artistic gymnastics, trampolining, handball)

Construction began: May 28, 2005

Completed: November 22, 2007

Capacity: 18,000 permanent, 2,000 temporary

- National Aquatics Centre (swimming, diving, synchronized swimming)

Construction began: December 24, 2003

Completed: delivered on January 28 2008

Capacity: 6,000 permanent, 11,000 temporary

Nicknamed the "Water Cube"

- Beijing Shooting Range

Construction began: July 13, 2004

Completed: July 28, 2007

Capacity: 2,170 permanent, 6,430 temporary

- Laoshan Velodrome (track cycling)

Construction began: October 30, 2004

Completed: December 2007

Capacity: 3,000 permanent, 3,000 temporary

- Beijing Olympic Basketball Stadium

Construction began: March 29, 2005

Completed: January 14, 2008

Capacity: 14,000 permanent, 4,000 temporary

- Shunyi Rowing/Canoeing Park

Construction began: May 2005

Completed: delivered on July 28, 2007

Capacity: 1,200 permanent, 25,800 temporary

- Beijing University of Technology Gymnasium (badminton, rhythmic gymnastics)

Construction began: June 30, 2005

Completed: September 30, 2007

Capacity: 5,767 permanent, 1,741 temporary

- China Agriculture University Gymnasium (wrestling)

Construction began: September 15, 2005

Completed: delivered on August 18 2007

Capacity: 6,000 permanent, 2,500 temporary

- University of Science and Technology Beijing Gymnasium (judo, taekwondo)

Construction began: November 18, 2005

Completed: November 2007

Capacity: 4,080 permanent, 3,932 temporary

- Peking University Gymnasium (table tennis)

Construction began: September 17, 2005

Completed: December 2007

Capacity: 6,000 permanent, 2,000 temporary

- Olympic Green Tennis Centre

Construction began: March 23, 2006

Completed: delivered on October 1, 2007

Capacity: 17,400

- Qingdao Olympic Sailing Centre

Construction began: May 2004

Completed: March 2008

Capacity: 9,000

- Qinghuangdao Olympic Sports Centre Stadium (soccer)

Construction began: May 2002

Completed: July 2004

Capacity: 33,000

- Tianjin Olympic Centre Stadium (soccer)

Construction began: August 2003

Completed: August 16, 2007

Capacity: 80,000

- Shenyang Olympic Sports Centre Stadium (soccer)

Construction began: March 1, 2006

Completed: July 2007

Capacity: 60,000

TEMPORARY

- Olympic Green Hockey Field (hockey)

Construction began: December 28, 2005

Completed: August 2007

Capacity: 17,000

- Olympic Green Archery Field (archery)

Construction began: December 28, 2005

Completed: August 2007

Capacity: 5,384

- Fencing Hall (fencing, modern pentathlon) Construction began: April 28, 2005

Completed: September 2007

Capacity: 5,900

- Wukesong Baseball Field

Construction began: December 22, 2005

Completed: August 2007

Capacity: 15,000

- Chaoyang Park Beach Volleyball Ground

Construction began: December 28, 2005

Completed: August 2007

Capacity: 12,200

- Laoshan Bicycle Moto Cross (BMX) Venue

Construction began: December 30, 2006

Completed: August 2007

Capacity: 4,000

- Triathlon Venue

Construction began: April 2007

Completed: September 2007

Capacity: 10,000

- Urban Road Cycling Course

Construction began: April 2007

Completed: April 2008

Capacity: 3,000

EXISTING

- Olympic Sports Centre Stadium (modern pentathlon)

Renovation began: April 1, 2006

Completed: September 2007

Capacity: 38,000 permanent, 2,000 temporary

- Olympic Sports Centre Gymnasium (handball)

Renovation began: April 1, 2006

Completed: September 2007

Capacity: 5,000 permanent, 2,000 temporary

- Workers' Stadium (soccer)

Renovation began: April 18, 2006

Completed: February 2008

Capacity: 62,000

- Workers' Indoor Gymnasium (boxing)

Renovation began: December 23, 2005

Completed: November 2007

Capacity: 12,000 permanent, 1,000 temporary

- Capital Indoor Stadium (volleyball)

Renovation began: May 18, 2006

Completed: November 2007

Capacity: 17,500

- Ying Tung Natatorium (water polo, modern pentathlon)

Renovation began: April 1, 2006

Completed: September 2007

Capacity: 4,852

- Laoshan Mountain Bike Course

Renovation began: May 31, 2006

Completed: September 2007

Capacity: 2,000 temporary seats, 15,000 standing

- Beijing Institute of Technology Gymnasium (volleyball)

Renovation began: February 8, 2007

Completed: September 2007

Capacity: 5,000

- Beijing University of Aeronautics and Astronautics Gymnasium (weightlifting)

Renovation began: January 31, 2007

Completed: December 2007

Capacity: 3,400 permanent, 2,600 temporary

- Beijing Shooting Range Clay Target Field

Renovation began: March 24, 2006

Completed: August 2007

Capacity: 3,394 permanent, 1,605 temporary

- Fengtai Softball Field (softball)

Renovation began: July 28, 2005

Completed: July 2006

Capacity: 5,000 permanent and 5,000 temporary seats

- Hong Kong Equestrian Venue (equestrian)

Renovation began: start of 2007

Completed: May 2007

Capacity: 20,000

- Shanghai Stadium (soccer)

Renovation began: 2006

Completed: 2007

Capacity: 56,000

(Compiled by Ian Ransom and Liu Zhen)

(For more stories visit our multimedia website "Road to Beijing" here; and see our blog at blogs.reuters.com/china)



More from Reuters

A security personnel stands guard near oil pipelines at Tawke oil field near Dahuk, 400 km (245 miles) north of Baghdad May 9, 2009. REUTERS/Azad Lashkari

Now or never for Big Oil

The pressure's on for oil giants looking to secure rare access to cheap Middle East reserves as Iraq gears up to auction off some of the world's largest untapped oilfields.  Full Article 

A glass of tap water is served at a restaurant in New York June 10, 2009 REUTERS/Shannon Stapleton

G7 glass half empty

Recovering from a punishing global recession has forced the world's richest nations to pay dearly, prompting subdued growth prospects and delayed sighs of relief.   Full Article