TOKYO, March 17 (Reuters) - The table below shows the
status of Japan's new nuclear power generators that are slated
to start operations over the coming years.
Capacities are shown in megawatts. "P" represents planned
commercial operations.
Company, plant Unit Capacity Status/start date
---------------------------------------------------------------
--------- Tokyo Electric Power Co (9501.T)
Fukushima-Daiichi No.7 1,380 Oct. 2014
No.8 1,380 Oct. 2015
Higashidori No.1 1,385 Dec. 2015
No.2 1,385 P from FY2018 or
after
---------------------------------------------------------------
---------- Chubu Electric Power Co (9502.T)
Hamaoka No.6 1,490* 2018-2022
---------------------------------------------------------------
---------- Kyushu Electric Power Co (9508.T)
Sendai No.3 1,590 April 2019-March
2020
---------------------------------------------------------------
---------- Tohoku Electric Power Co (9506.T)
Namie-Odaka N/A 825 April 2019-March
2020
Higashidori No.2 1,385 April 2019 or after
---------------------------------------------------------------
---------- Chugoku Electric Power Co (9504.T)
Shimane No.3 1,373 Dec. 2011 (under
construction)
Kaminoseki No.1 1,373 April 2015-March
2016
Kaminoseki No.2 1,373 April 2018-March
2019
---------------------------------------------------------------
---------- Hokkaido Electric Power Co (9509.T)
Tomari No.3 912 Dec. 2009(under
construction)
---------------------------------------------------------------
---------- Japan Atomic Power Co
Tsuruga No.3 1,538 Mar. 2016
Tsuruga No.4 1,538 Mar. 2017
---------------------------------------------------------------
---------- Electric Power Development Co (9513.T) (J-Power)
Ohma N/A 1,383 Nov. 2014 (under
construction)
* Reuters estimates
(Reporting by Osamu Tsukimori)