July 17, 2019 / 6:59 AM / a month ago

UPDATE 1-Fresnillo cuts 2019 output targets on lower ore grades

(Adds premarket indications, background, Q2 output numbers)

July 17 (Reuters) - Miner Fresnillo cut its output targets for 2019, citing lower-than-expected ore grades and delays in construction at its Herradura gold mine in Mexico after reporting a drop in second-quarter output from a year earlier.

The FTSE 100-listed company cut its 2019 gold production forecast to 880,000-910,000 ounces from a prior target of 910,000-930,000 ounces and silver production to 55-58 million ounces from 58-61 million ounces.

Fresnillo had said in May that 2019 would be more challenging than 2018 and that it was disappointed in not having met its long-term silver target of 65 million ounces.

The company on Wednesday reiterated the warning and said adjusted production costs for the first half was expected to be $135 million more than the same period a year ago due to lower ore grades and hurdles at its Herradura gold mine.

Fresnillo, Mexico’s largest gold producer, said gold production fell 5.4% to 221,307 ounces for the three months ended June 30, while silver production was 6% lower at 14.4 million ounces.

Premarket indicators have pegged the company’s shares to fall 4-5% at markets open. (Reporting by Muvija M in Bengaluru; editing by Patrick Graham and Arun Koyyur)

0 : 0
  • narrow-browser-and-phone
  • medium-browser-and-portrait-tablet
  • landscape-tablet
  • medium-wide-browser
  • wide-browser-and-larger
  • medium-browser-and-landscape-tablet
  • medium-wide-browser-and-larger
  • above-phone
  • portrait-tablet-and-above
  • above-portrait-tablet
  • landscape-tablet-and-above
  • landscape-tablet-and-medium-wide-browser
  • portrait-tablet-and-below
  • landscape-tablet-and-below